DCC 567/2020
In a dispute between a Subcontractor and Main contractor a settlement agreement had been signed after the original contract. This referred to a subcontract agreement with an arbitration clause in it. The key issue was whether the court had jurisdiction on the settlement agreement case.
Background
A dispute arose between a Subcontractor and Main Contractor. The Subcontractor filed a lawsuit against the Main Contractor before the Dubai Court of First Instance to claim 4,100,000 AED which was the outstanding payment balance. They relied on a settlement agreement the parties had signed at a later stage, which provided for payment of the outstanding balance by instalments.
The Main Contractor argued that the settlement agreement signed between the parties referred to a subcontract agreement which contained an arbitration clause and asked the Court of First Instance to refuse to hear the dispute because of a lack of jurisdiction. The Dubai Court of First Instance ruled in favour of the Subcontractor. This was upheld by the Court of Appeal.
Decision
The Dubai Court of Cassation referred to Article 5(3) of Federal Law No. 6/2018.