SCA 4530564462/2024
This case involved non-payment for completed subcontracted construction work. Issues included whether correct sign off of the project had occured. Evidence wa provided by oath. The limitation period for the appear was also considered.
Background
This case concerned a commercial dispute over a subcontracting contract for construction works, including excavation, compaction, and laying of base layers. The claimant, a subcontractor, had completed the contracted work and sought payment from the defendant for the remaining balance of 287,566 SAR. In addition, the claimant requested legal fees amounting to 15,000 SAR, representing 5% of the claim, citing the costs of pursuing the claim through the courts. The dispute centred on whether the claimant had fulfilled its contractual obligations and whether the defendant was legally obliged to settle the outstanding payment.