ADCC 280/2025

This case concerned a contractual dispute arising from the partial performance and delay in the construction of residential villas, where the appellant sought compensation and enforcement of contractual penalties.

Background

An Appellant filed Commercial Case No. 430/2024 before the Abu Dhabi Court of First Instance against four Respondents, seeking a ruling obliging the second, third, and fourth Respondents to jointly and severally pay AED 2,432,915, representing amounts already paid, along with 9% legal interest from 16 October 2018, and the daily penalty stipulated in the contract. Additionally, the Appellant requested that all four Respondents pay AED 1,000,000 in compensation for delays in contract execution.